On June 4, 2025, at approximately 2:19 p.m. local time, an explosion and fire occurred in Furnace 5 of the ethane cracking unit at the Shell Polymers Monaca facility in Monaca, Pennsylvania. The explosion severely damaged Furnace 5 and was followed by a fire, releasing an estimated 5,100 pounds of ethylene and combustion products. Fifteen employees evacuated the area. Shell estimated approximately $95 million in property damage. No fatalities or injuries were reported.
The Shell Polymers Monaca facility — a $6 billion petrochemical complex that began operations in 2022 — converts ethane to ethylene through a high-temperature cracking process in an ethane cracking unit containing seven furnaces. During normal operation, a solid carbon residue known as coke accumulates in coke traps designed to prevent the material from migrating downstream. In early 2025, during a planned unit outage, Shell discovered that the coke traps in all seven furnaces required cleaning — a task that had never been performed at the facility since its startup.
As Furnace 5 was being returned to service after its coke trap cleaning on June 3–4, 2025, a process control engineer inadvertently opened both motor-operated valves (MOVs) that had been isolating the furnace from the downstream cracked gas system. The process control engineer assigned to this task had never performed it before and had limited knowledge of the process. When both isolation valves were simultaneously opened, flammable cracked gas backflowed from the downstream quench tower through the unintended flow path into the furnace firebox, where it contacted lit pilot burners and ignited approximately six minutes later — causing the explosion that ruptured the firebox wall and triggered the subsequent fire.
Furnace 5 was repaired and returned to service approximately seven months after the incident. The CSB's final report, released September 16, 2026, found that despite Shell's process hazard analysis having previously identified cracked gas backflow as a potentially fatal hazard, the facility relied solely on administrative controls — specifically 11 procedure-based controls — rather than implementing engineered safeguards. Available engineered controls provided by the furnace technology licensor were not configured for use during the removal of double isolation.
The Shell Polymers incident is a case study in how PSM elements interact — and how gaps in multiple elements compound into a single catastrophic event. Here is how each failed element connects to 29 CFR 1910.119.
SafeGuard PSM is a process safety consulting firm specializing in OSHA 29 CFR 1910.119 compliance. We work with chemical facilities, refineries, and industrial operators to build, improve, and audit PSM programs that protect workers and communities.
Our case study library covers every completed CSB investigation — analyzed through the lens of the 14 PSM elements so your team can learn from industry incidents and apply those lessons to your own facility.
Visit SafeGuard PSM ↗