Overpressure Release — PSV Discharge to Unsafe Location
Kuraray America EVAL Plant Ethylene Release and Fire
Kuraray America, Inc.
📍 Pasadena, TX
Incident: May 19, 2018  •  CSB Report: December 21, 2022
0
Fatalities
Ethylene (~2,300 lbs, High Pressure via PSV)
Chemical / Hazard
12
CSB Recommendations
📋 Incident Summary

On May 19, 2018, a high-pressure ethylene release and fire at the Kuraray America EVAL resin plant in Pasadena, Texas, injured 21 workers. EVAL Reactor 2 was being restarted after a maintenance outage when a pressure safety valve (PSV) activated, releasing approximately 2,300 pounds of high-pressure ethylene through a discharge line terminating in an open area where contractor workers were present.

The ethylene ignited, causing a flash fire that burned contractors positioned near the PSV discharge location. The CSB found that startup procedures did not adequately control conditions to prevent PSV activation, that the PSV discharge routed ethylene to an unsafe location, and that contractors were not warned of the potential for a high-pressure ethylene release.

The December 2022 CSB report issued 12 recommendations to Kuraray America. As of October 2026, the CSB lists eleven as closed and one as open. They cover emergency relief discharge locations, keeping nonessential personnel away during upsets and startup, safeguard evaluation, recommendation management, operating procedures and training, alarm management, safe operating limits, and an independent PSM assessment.

🔎 Key Findings
Finding 01
PSV Discharged Ethylene to Occupied Area
The PSV on Reactor 2 discharged ~2,300 lbs of high-pressure ethylene through a line terminating in an open location accessible to workers — contractors were present in the discharge zone with no warning.
Finding 02
Startup Procedure Did Not Prevent Overpressure
The reactor restart procedure allowed conditions that resulted in overpressure and PSV activation — it did not include adequate controls or monitoring to prevent a PSV event during post-maintenance startup.
Finding 03
Contractors Not Warned of PSV Release Hazard
Contractor workers near the PSV discharge location were not informed of the potential for a high-pressure ethylene release during startup — they had no warning before the release began.
Finding 04
MOC Did Not Address Post-Maintenance Startup Risk
The change associated with the Reactor 2 maintenance outage and restart was not evaluated through a formal MOC process that would have identified the heightened overpressure risk.
Finding 05
Flash Fire Injured 21 Workers
The ethylene cloud ignited rapidly; the resulting flash fire caused burn injuries to 21 workers, primarily contractors closest to the PSV discharge location.
🔍 Root Causes
1
Inadequate Startup Procedure for Post-Maintenance Restart
Operating procedures for restarting Reactor 2 after maintenance did not reflect the different risk profile of a first-start-after-maintenance versus a routine restart — no additional controls were specified.
2
PSV Discharge Routed to Occupied Area
The PSV discharge system design terminated ethylene releases in an accessible work area without providing a safe dispersion path, vapor barriers, or restricted access.
3
Contractor Safety Program Did Not Address Process Hazards
The contractor safety management program did not ensure workers near the PSV discharge were briefed on specific process hazards associated with the nearby reactor restart.
☑ CSB Recommendations
→ Kuraray America
Develop and implement an emergency pressure-relief system design standard so each relief system discharges to a safe location, with periodic evaluation of existing systems. [Open]
→ Kuraray America
Implement a site-wide system to evacuate nonessential personnel during upsets and keep them away from equipment during transient operations such as startup. [Closed]
→ Kuraray America
Develop a system requiring periodic evaluation of the adequacy and effectiveness of safeguards, based on Cal/OSHA refinery PSM regulations or an equivalent method. [Closed]
→ Kuraray America
Develop a policy for effectively addressing recommendations from audits, incident investigations, MOC, and PHA, with periodic training for those who evaluate them. [Closed]
→ Kuraray America
Review CCPS guidance on catastrophic incident warning signs and build a warning-signs program into the EVAL Plant safety management system. [Closed]
→ Kuraray America
Clarify the lower design pressure of EVAL Reactor 2 in training, written procedures, and the control system interface. [Closed]
→ Kuraray America
Ensure nightly operating instructions do not conflict with written procedures, use MOC for procedure changes, and write and train on the reactor methanol flush procedure. [Closed]
→ Kuraray America
Strengthen operator training on known activities, upset conditions, alarm responses, use of the emergency open valve, and safe operating limits. [Closed]
→ Kuraray America
Complete alarm management efforts and maintain alarm rates at or below ISA 18.2 performance targets. [Closed]
→ Kuraray America
Improve the safety management system for startup and abnormal conditions, including liquid ethylene accumulation, alarm response, and removing restrictions on the emergency open valve. [Closed]
→ Kuraray America
Modify the safe operating limits program to prevent operating under conditions that rely on equipment design safety factors, such as ASME code margins. [Closed]
→ Kuraray America
Hire an independent third party to perform a comprehensive assessment of the EVAL Plant's process safety management systems. [Closed: Acceptable Alternative Action]

Full recommendation text and current status: CSB investigation page.

💡 Lessons Learned
Pressure safety valves are critical safeguards — but where they discharge matters as much as whether they open. Routing PSV discharges to worker-accessible locations turns a protection success into an exposure event.
Post-maintenance startups carry inherently higher risk than routine restarts. Procedures must be specifically designed for first-start-after-maintenance scenarios, not repurposed from normal startup sequences.
Contractors working near active process operations must be explicitly briefed on the specific hazards at their work location — generic safety orientation is not a substitute for task-specific hazard communication.
Management of Change must evaluate not just the maintenance work performed, but the startup that follows. The first restart after maintenance is itself a change that requires hazard review.
PSSRs are required by PSM before introducing highly hazardous chemicals. Treating post-maintenance restarts as equivalent to routine startups bypasses this critical safeguard.
SOP: Operating ProceduresMOC: Management of ChangeTRN: TrainingPHA: Process Hazard Analysis
🔨 Safety Meeting Toolbox Talk
►Do you know where the pressure relief valves on your unit discharge — and whether anyone could be in that area during a release?
►When we restart a unit after maintenance, do we use the same procedure as a routine startup, or a specific post-maintenance procedure with additional controls?
►Before contractors begin work near active process equipment, how do we communicate the specific hazards present at their work location that day?
►Has your facility ever experienced a PSV activation during startup? If so, was that scenario evaluated in the PHA?
►How does your MOC process address the restart phase after maintenance — is the startup itself evaluated as part of the change review?
Immediate Action Items
✓Walk down the PSV discharge locations for your highest-risk process units and verify they discharge to safe areas inaccessible to workers during operations.
✓Pull your post-maintenance startup procedures for one critical unit and compare them to routine startup procedures — identify any hazard-specific controls that are missing.
✓Review your contractor pre-job briefing process to confirm that process-specific hazards at the work location are communicated before work begins.
✓Confirm that your facility's MOC procedure requires startup hazard review as part of return-to-service planning for post-maintenance work.
✓Identify any unit where a PSV activation during startup could expose workers to flammable or high-pressure materials and develop a corrective action plan.
🔗 PSM Failures Behind This Incident

This incident traced to breakdowns across 4 PSM elements (SOP · MOC · TRN · PHA). Each represents a documented gap that process safety documentation and consulting can close before a similar event occurs at your facility.

Operating Procedures (SOPs)
Operators cannot reliably hold safe operating limits without clear, current, enforced procedures. Deviation from acceptable operating conditions — a root cause here — is a direct consequence of SOP failure.
Supporting documents in our library →
Management of Change (MOC)
Changes to equipment, chemistry, operating limits, or procedures that bypass formal review create new hazard pathways your PHA never evaluated. MOC failures open the door to incidents like this one.
Supporting documents in our library →
Training & Operator Competency
Workers must understand process hazards — not just the steps on the page. Training records, refresher frequency, and verified competency are all OSHA PSM requirements that gaps here violated.
Supporting documents in our library →
Process Hazard Analysis (PHA)
A structured PHA or HAZOP study exists to identify exactly these scenarios before they occur. When PHA is absent, superficial, or overdue for revalidation, hazards operate unseen until they kill someone.
Supporting documents in our library →
Process Safety Management Consulting & Document Library
📂
PSM Document Library
72 ready-to-deploy PSM documents covering all 14 OSHA elements — procedures, checklists, and audit templates built for facilities operating under 29 CFR 1910.119.
Browse the Library →
📊
Free PSM Health Score
Find out where your PSM program stands across all 14 OSHA elements. Our free health score surfaces your biggest gaps in under 10 minutes — no account required.
Check Your Score →
📞
Consulting Services
PHA facilitation, PSM program builds, compliance audits, and OSHA inspection support. Scoped per project with a written proposal before work begins — no retainer required to get started.
View Pricing →
📋 Explore the full incident library: All 111 CSB Case Studies →