Explosives Manufacturing — Investigation Ongoing
Accurate Energetic Systems Fatal Explosions
Accurate Energetic Systems (AES)
📍 McEwen, TN
Incident: October 10, 2025 • CSB Report: Investigation ongoing (update released March 2026)
16
Fatalities
7
Injured
Explosive Materials (~23,000 lb) — Melt-Pour Cast Booster Production
Chemical / Hazard
Pending
CSB Recommendations
📋 Incident Summary

On October 10, 2025, explosions destroyed Building 602 at the Accurate Energetic Systems facility in McEwen, Tennessee. Sixteen employees working in the building were killed and seven others nearby were injured. The CSB estimates that about 23,000 pounds of material detonated, deflagrated, or burned.

Workers were making cast boosters using a melt-pour process: explosive materials were melted in steam-jacketed kettles on a mezzanine level and the molten mixture was poured by hand into tubes. The CSB said the first detonation created a pressure wave that set off additional explosives throughout the building. The building had no sprinkler or deluge fire protection system.

The CSB investigation is ongoing. Its March 2026 update did not state a cause. The CSB is examining AES's production process, its process safety management programs for explosives, and the design and operation of the melt-pour kettles. No recommendations have been issued yet.

🔎 Key Findings
Finding 01
Melt-Pour Process
Explosive materials were melted in steam-jacketed kettles and poured by hand into tubes to make cast boosters.
Finding 02
Propagation Through the Building
The first detonation's pressure wave set off additional explosives throughout the building.
Finding 03
Large Quantity Involved
About 23,000 pounds of material detonated, deflagrated, or burned.
Finding 04
No Sprinkler or Deluge System
Building 602 was not equipped with a sprinkler or deluge fire protection system.
Finding 05
Cause Not Yet Determined
The CSB has not stated a cause; its investigation continues.
🔍 Root Causes
1
Under investigation
The CSB has not yet determined the cause.
2
Areas being examined
Production process, process safety management for explosives, and kettle design and operation.
3
Final report pending
Findings and any recommendations will be in the CSB's final report.
☑ CSB Recommendations
→ Investigation ongoing
The CSB has not issued recommendations. Findings and any recommendations will be published in its final report. Check the CSB investigation page for updates.

Full recommendation text and current status: CSB investigation page.

💡 Lessons Learned
Limit the quantity of explosives in any one building and the number of people exposed.
Separate operations so one event cannot propagate through a building.
Processes that heat energetic materials need rigorous hazard analysis and controls.
Watch for the CSB's final report and apply its findings.
PHA: Process Hazard AnalysisSOP: Operating ProceduresMI: Mechanical IntegrityEAP: Emergency Planning
🔨 Safety Meeting Toolbox Talk
Topic: Explosive Manufacturing Process Safety & Blast Isolation
►How much energetic material is in each of our buildings at once?
►How many people are exposed to each operation?
►Could one event propagate to others nearby?
►How are heating systems for energetic materials controlled?
Immediate Action Items
✓Review quantity limits and personnel exposure in hazardous buildings.
✓Evaluate separation and propagation risks.
✓Follow the CSB investigation for final findings.
🔗 PSM Failures Behind This Incident

This incident involved breakdowns across 4 PSM-related areas (PHA · SOP · MI · EAP). Each represents a gap that process safety programs are designed to close.

Process Hazard Analysis (PHA)
A structured PHA or HAZOP study exists to identify exactly these scenarios before they occur. When PHA is absent, superficial, or overdue for revalidation, hazards operate unseen until they kill someone.
Supporting documents in our library →
Operating Procedures (SOPs)
Operators cannot reliably hold safe operating limits without clear, current, enforced procedures. Deviation from acceptable operating conditions is a direct consequence of SOP failure.
Supporting documents in our library →
Mechanical Integrity (MI)
Equipment must be designed, inspected, and maintained to operate safely in its intended service. Mechanical integrity failures contributed to loss of containment here.
Supporting documents in our library →
Emergency Planning & Response
When process safety barriers fail, emergency response capability determines whether the outcome is controlled or catastrophic. Gaps in emergency preparedness amplified the consequences here.
Supporting documents in our library →
Process Safety Management Consulting & Document Library
📂
PSM Document Library
72 ready-to-deploy PSM documents covering all 14 OSHA elements — procedures, checklists, and audit templates built for facilities operating under 29 CFR 1910.119.
Browse the Library →
📊
Free PSM Health Score
Find out where your PSM program stands across all 14 OSHA elements. Our free health score surfaces your biggest gaps in under 10 minutes — no account required.
Check Your Score →
📞
Consulting Services
PHA facilitation, PSM program builds, compliance audits, and OSHA inspection support. Scoped per project with a written proposal before work begins — no retainer required to get started.
View Pricing →
📋 Explore the full incident library: All 111 CSB Case Studies →