SafeGuard Projects
SafeGuard ProjectsCapital Projects
OSHA 1910.119
OSHA 1910.119Free PSM Resource
California · Cal/OSHA PSM · CalARP

PSM & CalARP Compliance
in California.

California runs its own process safety programs. Worker safety falls under Cal/OSHA's PSM regulation (Title 8, §5189, and §5189.1 for refineries). Community protection falls under the California Accidental Release Prevention (CalARP) program, enforced by your local Unified Program Agency. Knowing only the federal rules leaves gaps. Here is how the California programs are built, with every point linked to the official text.

Two Programs, Two Regulators

Who Regulates What in California

Many California facilities fall under both programs at once. One protects workers inside the fence; the other protects the community and environment outside it.

Cal/OSHA PSMCalARP
RegulationTitle 8 CCR §5189 (general industry); §5189.1 (petroleum refineries, operative Oct 1, 2017)Title 19 CCR, Division 5, Chapter 2, §§5050.1–5160.1; Health & Safety Code §§25531–25543.3
ProtectsEmployeesThe public and the environment
Who enforcesCal/OSHA (Department of Industrial Relations)Overseen by CalEPA (transferred from Cal OES in July 2021); implemented locally by Unified Program Agencies (CUPAs)
Federal counterpartOSHA 29 CFR 1910.119 (California is a state-plan state)EPA RMP, 40 CFR Part 68. If a federally listed substance exceeds its threshold, the RMP goes to both EPA and the local UPA
Watch the citations. CalARP regulations were renumbered effective March 6, 2024, moving from Title 19, Division 2, Chapter 4.5 (§§2735–2785) to Division 5, Chapter 2 (§§5050.1–5160.1). CalEPA states the renumbering did not materially change any requirement. Older procedures and RMPs may still cite the old numbers. CalEPA publishes a crosswalk (Guidance Document 24-01).
Cal/OSHA §5189

Where §5189 Differs from Federal PSM

§5189 covers the same core elements as 29 CFR 1910.119, but several requirements are worded differently. These are the differences most likely to trip up a program written to the federal standard.

Coverage
A process with a chemical at or above its threshold in §5189 Appendix A (California's own list, last amended 2020), or a Category 1 flammable gas or flammable liquid with a flashpoint below 100°F, in a quantity of 10,000 lb or more. Check your chemicals against California's Appendix A, not just the federal list. [§5189(b)(1)]
Incident investigation trigger
Every incident that resulted in, or could reasonably have resulted in, a "major accident": a fire, explosion, or release causing a fatality or serious injury (Labor Code §6302). Federal PSM keys on a "catastrophic release." Investigations start within 48 hours; reports are kept 5 years. [§5189(c), (m)]
Employee reporting of faulty equipment
Mechanical integrity procedures must include a way for employees to identify and report potentially faulty or unsafe equipment, record their observations in writing, and get a timely response. [§5189(j)(1)]
Tied to your IIPP
Your Injury and Illness Prevention Program (Title 8 §3203) must include the applicable parts of §5189. Scheduled inspections of covered facilities must be done by at least one person knowledgeable in the process. [§5189(o)]
Information access
Employees and their representatives get access to all required PSM information "without regard to possible trade secret status." Confidentiality agreements are allowed. Federal PSM handles this in a separate trade secrets paragraph. [§5189(p)]
Emergency planning
An Emergency Action Plan under Title 8 §3220 (federal: 1910.38). The HMBP business plan may be used to the extent it meets the requirement. [§5189(n)]
Union and employee consultation
Employers consult affected employees and, where appropriate, their recognized representatives on hazard assessments. The PHA report must be available in the work area. [§5189(e)(3)]
Compliance audits
§5189 has no compliance-audit subsection like federal 1910.119(o). Processes in CalARP Programs 2, 3, or 4 have compliance-audit requirements under Title 19 (§§5090.6, 5100.8, 5110.11). Confirm which apply to your facility.
CalARP Essentials

How CalARP Goes Beyond Federal RMP

Three substance tables
Table 1 (federal toxics), Table 2 (federal flammables), and Table 3, a state-only list (19 CCR §5130.6). For Table 3 substances above threshold, an RMP is required when the UPA determines one is needed under HSC §25534.
Program 3 tied to Cal/OSHA
A process is Program 3 if it isn't Program 1 and it is in a listed NAICS code (322110, 325110, 325180, 325194, 325199, 325211, 325311, 325320), is subject to Cal/OSHA §5189, or the UPA requires it for a Table 3 substance. [19 CCR §5050.4(e)]
External events and seismic
CalARP RMPs report the natural and human-caused external events considered in the PHA or hazard review, their estimated magnitude, seismic parameters and the Building Code edition used when the process was designed (where seismic applies), and the date equipment was last field-verified as installed and maintained as designed. [e.g., 19 CCR §5070.6(l)]
Local regulator
Your local CUPA reviews the RMP, sets the level of detail it expects, inspects, and provides public access. CalEPA notes local requirements may be more stringent than the state's.
SB 740: workforce for new energy
Effective Jan 1, 2024 (HSC §25536.8). RMP stationary sources that manufacture hydrogen, biofuels, or certain specified chemicals, or capture, sequester, or use CO2, must require contractors to use a skilled and trained workforce for construction, alteration, repair, and maintenance work. This matters for SAF, hydrogen, and carbon-capture projects in California.
Program 4: refineries
All processes in petroleum refineries (NAICS 324110), with expanded prevention requirements and an annual Process Safety Performance Indicator report due June 30 to CalEPA and the UPA. CalEPA listed 11 active refineries in 2024. CalEPA approved further Program 4 amendments in 2026 (including Hierarchy of Hazard Control Analysis and employee participation); check the current text.
Refineries: §5189.1

What California Requires of Refineries

After the 2012 Chevron Richmond refinery fire, California adopted §5189.1, which replaces §5189 for petroleum refineries. It goes well beyond federal PSM.

RequirementWhat it adds
Damage Mechanism Review (DMR)For each process where a damage mechanism exists; revalidated at least every 5 years and reviewed for major changes. [§5189.1(k)]
Hierarchy of Hazard Controls Analysis (HCA)A standalone analysis using the hierarchy: first-order inherent safety, second-order inherent safety, then passive, active, and procedural protection layers. Also required for PHA recommendations on major-incident scenarios and for major-incident investigation recommendations. Revalidated every 5 years. [§5189.1(c), (l)]
Safeguard Protection Analysis (SPA)For every PHA scenario with major-incident potential, a written quantitative or semi-quantitative analysis (such as LOPA) of how effective each safeguard is, completed within 6 months of the PHA. [§5189.1(e)(5)]
Process Safety Culture AssessmentA written assessment at least every 5 years, by a team including an employee representative. [§5189.1(r)]
Human Factors programWritten analysis in major changes, incident investigations, PHAs, MOOCs, and HCAs; assessment of operating and maintenance procedures. [§5189.1(s)]
Management of Organizational Change (MOOC)Required before reducing staffing or classification levels, changing shift duration, or increasing responsibilities by 15% or more, for changes over 90 days. [§5189.1(t)]
Stop Work authorityIncluding contractor employees, as part of the employee participation program. [§5189.1(q)]
Root cause analysisIncident investigations use root cause analysis. [§5189.1(o)]
Corrective action programTeam recommendations may be rejected only for documented reasons: material factual errors, not relevant to process safety, or infeasible ("not based solely on cost"). Changes and rejections go back to the team for comment. [§5189.1(x)]
Compliance auditsEvery 3 years, with documented operator consultation and a written response to comments within 60 days. [§5189.1(u)]

Operating in California?

SafeGuard PSM helps California facilities line up federal PSM, Cal/OSHA §5189, and CalARP. We facilitate PHAs and HAZOPs, run gap assessments against the California-specific requirements, and support compliance audits.

Talk to Us See a HAZOP Worked Example Free PSM Assessment
Not legal advice. This page summarizes California regulations as published by Cal/OSHA (DIR) and CalEPA as of October 2026. Regulations change, and your local UPA may have additional requirements. Always confirm against the current official text and with your regulator or counsel.
Sources

Title 8 CCR §5189, Process Safety Management of Acutely Hazardous Materials: dir.ca.gov
Title 8 CCR §5189.1, Process Safety Management for Petroleum Refineries: dir.ca.gov
CalARP regulations, Title 19 CCR Division 5 Chapter 2 (CalEPA compilation, Sept 2026): calepa.ca.gov (PDF)
CalARP Program Levels, Program 4, FAQ, Program Updates, and Resources: calepa.ca.gov/california-accidental-release-prevention
CalARP Program 4 amendments, Notice of Exemption, March 2, 2026: ceqanet.lci.ca.gov
Federal comparisons: 29 CFR 1910.119 and 40 CFR Part 68.

The SafeGuard Family:   SafeGuard PSM  ·  SafeGuard Projects  ·  OSHA1910119.com